Anchored Retail Center Site Preparation
5 months
North Side, ST
Site Clearing & Demolition, Mass Grading & Earthwork +1 more
38 acres cleared & graded
The site had significant elevation changes requiring a large balanced cut/fill operation. Three detention basins had to be constructed concurrently with grading to satisfy the City drainage permit conditions — adding schedule complexity.
We sequenced the earthwork to use cut material directly in constructing detention basin berms, eliminating haul-off cost and compressing the schedule. Basin grading and storm sewer installation ran parallel with mass earthwork through a coordinated two-crew operation.
Site delivered to general contractor within the contractual window. Detention basins passed the City inspection on first submittal. Earthwork quantities balanced within 2% of the civil engineer's design volumes.