HospitalitySite Preparation

Select-Service Hotel Pad Preparation

Central District, ST
Duration

6 weeks

Location

Central District, ST

Services

Site Clearing & Demolition, Earthwork & Grading +2 more

Scope

4.5-acre infill site

4.5-acre infill site
Pad certified in 6 weeks
Existing structure demolished
Tight urban site clearances
The Challenge

The site was a constrained urban infill lot with an existing slab, underground utility conflicts identified during potholing, and neighboring properties within 10 feet on two sides. The developer had a hard financing deadline requiring pad certification on a specific date.

Our Approach

A pre-construction utility scan identified all underground conflicts before mobilization, allowing re-sequencing without schedule impact. Demolition and utility conflict resolution ran concurrently. Shoring was installed along the tight property lines to protect adjacent infrastructure.

The Outcome

Pad delivered and geotechnically certified on the exact financing deadline. Zero incidents. No damage to adjacent properties. The developer returned four months later with a second hotel site.